0 minutes unplanned downtime

Zero-downtime cloud migration for a 24/7 manufacturer

How Atlas migrated 146 workloads off an aging data center to Azure — without ever stopping a plant.

Client
Atlas Manufacturing
Industry
Manufacturing
Timeline
10 months of phased cutovers
Business impact

Results at a glance

0 min
Downtime
0%
Infra spend
0
Workloads moved
0x
RTO improvement
Situation

Where they started

  • Data center reaching end-of-life within 18 months.
  • 80+ integrations, many undocumented.
  • Plants run 24/7 — no downtime tolerated.
Approach

How we did the work

  1. 1

    Dependency discovery

    Full inventory before touching production.

  2. 2

    Strangler-fig migration

    One bounded context at a time, reversible cutovers.

  3. 3

    Platform foundations

    Terraform landing zones, day-one observability, cost guardrails.

Results

What changed

Zero unplanned downtime across all cutovers.

Infra spend down 27% after right-sizing.

Recovery time objectives improved 18x.

Technology

Tools of the trade

Azure
Terraform
Kubernetes
Datadog
SAP
Kafka

"They treated our uptime like their own. Every cutover was boring — which is exactly what we wanted."

Sonia MarchettiCIO, Atlas Manufacturing
Book a consultation

Bring us your hardest problem

30 minutes with our senior specialists. No decks — just a working conversation.

We reply within one business day. Your information is kept confidential and never shared.

Ready to amplify your data?

Book a 30-minute strategy call. We'll map your data landscape and identify the three highest-leverage moves.

See case studies